Schedule Gantt in Aire
A project schedule lives in the model as schedule blocks: each activity has a start, a duration in days, and the activities it waits on. The Schedule Gantt draws that schedule as a chart, so the same terms that drive your financial model also show you when things happen.- Every schedule block with a start and a duration becomes a bar
- Sections roll their activities up into one bar
- The critical path is marked, and a lag between linked activities moves it
- Edit an activity on the chart and the model updates
Starting a schedule
Choose Add schedule block and start from one of nine reviewed templates, or from an empty block:- Solar, at concept stage or in development
- Battery storage: utility scale, commercial and industrial, behind the meter, or front of the meter at concept stage
- Solar with battery storage, at concept stage
- Industrial, at concept stage or in development